Barton makes the earth move at MPMK

August 23, 2017

Barton are back in action for IDI Gazeley at their flagship distribution site, Gallagher Logistics Park at Magna Park Milton Keynes. As the contracting arm of The Bennie Group, main contractor Barton have thrown an impressive team and fleet of their own kit at the job to meet the challenging 24 week programme.

In excess of 270,000 cu m of soil will be moved as part of a complete infrastructure package on this high-profile scheme. Fellow group company, Peter Bennie Ltd are supplying the project with over 100,000 tonnes of stone from their nearby Wroxton Quarry to further demonstrate the significant benefit and value being delivered by The Bennie Group.

The busiest single day so far saw an impressive 3600 tonnes of stone delivered and profiled by the team with plenty more to follow.

 